EIA Notifications Environmental Clearance - General

Print

Status of Total Cases of Consent to Establish (NOC) & Consent to Operate under consideration for disposal as on Sept. 04, 2012)

A. Status of disposal of application received as on May 04, 2012

  Consent to Operate Consent to Establish (NOC)
RO, Dehradun 17 09
RO, Haldwani 07 03
RO, Roorkee 79 02
RO, Kashipur 97 02
Total 200 16

B.  Status of disposal of application received as on Sept. 04, 2012 

  Consent to Operate Consent to Establish (NOC)
RO, Dehradun 115 19
RO, Haldwani 26 06
RO, Roorke 368 08
RO, Kashipur 256 09
Total 765 42

* As per Water Act, 1974 and Air Act, 1981, four month time is stipulated for processing the cases of consent and this is the normal processing time.

 

Status of Total Cases of Consent to Establish (NOC) & Consent to Operate under consideration for disposal

A. As on March 31, 2012

  Consent to Operate Consent to Establish (NOC)
RO, Dehra Dun 34 11
RO, Haldwani 08 01
RO, Roorkee 115 04
RO, Kashipur 160 05
Total 317 21

B.  As on July 17, 2012*

  Consent to Operate Consent to Establish (NOC)
RO, Dehradun 141 21
RO, Haldwani 42 6
RO, Roorke 366 09
RO, Kashipur 296 15
Total 845 51

* As per Water Act, 1974 and Air Act, 1981, four month time is stipulated for processing the cases of consent and this is the normal processing time.


 


Consent to Operate
Consent to Establish (NOC)
RO, Dehra Dun
34
11
RO, Haldwani
08
01
RO, Roorkee
115
04
RO, Kashipur
160 05
Total
317
21